Oracle sends a force majeure notice on its Project Jupiter data center in New Mexico and says the schedule is unchanged

Current status
Corroborated
Companies
Oracle, Blue Owl (counterparty), OpenAI (mentioned)
Happened
Sep 24, 2026
Last updated
Sep 25, 2:50 PM PT (revision 1)
Evidence
5 reports · 2 independent chains (adjudicated)

What happened

Oracle sent developer Blue Owl a force majeure notice on the 2.45 GW Project Jupiter campus, a Stargate site. The clause would let Oracle delay payments if the site misses its 2028 launch target. The gas pipeline meant to fuel the site's fuel cells has been pushed to February 2027 after permit rejections. Oracle says the project remains on its planned schedule, and Blue Owl says its financial commitments are unchanged. Oracle shares fell about 3%.

Why it matters

It's the clearest sign yet of delivery and power risk at a Stargate site that OpenAI's capacity plans depend on. It also puts the terms of AI data-center financing to a live test.

Uncertainty

Whether the 2028 date actually slips is unresolved. Oracle says no delay is expected, while the notice itself keeps the option to delay payments open. Reuters' sources describe knock-on effects for AI financing; we haven't reviewed that article in full.

Evidence and provenance

  1. First reportchain: bloomberg
    Oracle cites 'force majeure' to shield itself on controversial data center
    Bloomberg · published Sep 24, 2026 · paywall · bloomberg.com · rev 1
  2. Corroborationchain: reuters
    Oracle, Blue Owl project delay sends ripples through AI financing, sources say
    Reuters · published Sep 24, 2026 · reuters.com · rev 1
  3. Context
    Oracle invokes 'force majeure' on Project Jupiter, but says data center still on track
    Albuquerque Journal · published Sep 24, 2026 · abqjournal.com · rev 1
    Carries Oracle's statement that the project remains on schedule.
  4. Coverage
    Oracle sends force majeure notice on its New Mexico Stargate data center
    TechCrunch · published Sep 24, 2026 · techcrunch.com · rev 1
  5. Coverage
Oracle sends a force majeure notice on its Project Jupiter data center in New Mexico and says the schedule is unchanged · Globe Examiner